A. Sort the risks according to their impact.
B. Perform a qualitative risk analysis.
C. Identify what risks have the highest probability.
D. Perform a quantitative risk analysis.
Activity A takes one day
Activity B follows A and takes five days
Activity C follows B and takes two days.
Activity D follows B and A takes two days.
Activity E is preceded by C and D and takes two days.
What would be the critical path(s)?
A. A-B-C-E and A-B-D-E
B. A-B-C-E and A-D-E
C. A-B-D-E
D. A-D-E and A-B-D-E
What should the project manager do?
A. Ask the stakeholder how the additional information that they feel is missing from current communications may be provided.
B. Keep the team member properly informed about project status so that the stakeholder receives the same information from both sources.
C. Leave the connection in place, since the information coming via the team member is unofficial and will not create problems.
D. Tell the team member not to accept calls from the stakeholder, because these calls have an adverse effect on the team members productivity.
What should the project manager do?
A. Conduct a probability and impact assessment.
B. Allow any issues to be handled by management.
C. Adjust the schedule to include time for handling objections.
D. Create the project management plan and wait to act until issues actually occur.