Project Management Professional (PMP) Exam Practice – Question0421

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?


A.
Communications management plan
B. Human resource plan
C. Quality management plan
D. Procurement management plan

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question0416

Which of the following are three inputs to the risk register?


A.
Risk register updates, stakeholder register, and quality management plan
B. Communication management plan, enterprise environmental factors, and activity duration estimates
C. Risk management plan, activity cost estimates, and project documents
D. Project scope statement, organizational process assets, and scope baseline

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question0414

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?


A.
Initiating
B. Planning
C. Executing
D. Monitoring and Controlling

Correct Answer: B