Project Management Professional (PMP) Exam Practice – Question0392

Which of the following are outputs of Develop Project Team?


A.
Human resources plan changes and project staff assignment updates
B. Project management plan updates and enterprise environmental factor updates
C. Resource calendars and project management plan updates
D. Team performance assessments and enterprise environmental factor updates

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question0391

Tools and techniques used for Plan Communications include the communication:


A.
requirements analysis, communication technology, communication models, and communication methods.
B. methods, stakeholder register, communication technology, and communication models.
C. requirements, communication technology, communication requirements analysis, and communication methods.
D. management plan, communication technology, communication models, and communication requirements analysis.

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question0383

When can pre-assignment of project team members occur?


A.
When the project uses capital expenditures
B. When the required staff can be acquired from outside sources
C. When the project would be ignored due to travel expenses
D. When the project is the result of specific people being promised as part of a competitive proposal

Correct Answer: D