Project Management Professional (PMP) Exam Practice – Question0370

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?


A.
The customer and functional managers
B. The risk owners and stakeholders
C. The sponsors and stakeholders
D. The project management team

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question0364

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?


A.
Project Integration Management
B. Project Communications Management
C. Project Information Management System (PIMS)
D. Project Scope Management

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question0363

Which of the following statements correctly characterizes pull communication?


A.
It includes letters, memos, reports, emails, and faxes.
B. It requires recipients to access communication content at their own discretion.
C. It is the most efficient way to ensure a common understanding among all participants.
D. It is primarily used when the volume of information to be transferred is minimal.

Correct Answer: B