Project Management Professional (PMP) Exam Practice – Question0362

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?


A.
Complete project phase
B. Project life
C. The project life cycle
D. Project cycle

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0362

Project Management Professional (PMP) Exam Practice – Question0361

Which of the following is a tool and technique for Estimate Activity Durations?


A.
Parametric estimating
B. Monte Carlo analysis
C. Alternatives analysis
D. Bottom-up estimating

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0361

Project Management Professional (PMP) Exam Practice – Question0360

Which of the following is contained within the communications management plan?


A.
An organizational chart
B. Glossary of common terminology
C. Organizational process assets
D. Enterprise environmental factors

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0360

Project Management Professional (PMP) Exam Practice – Question0359

When is a Salience Model used?


A.
In a work breakdown structure (WBS)
B. During quality assurance
C. In stakeholder analysis
D. During quality control (QC)

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0359

Project Management Professional (PMP) Exam Practice – Question0358

What is an objective of the Develop Project Team process?


A.
Feelings of trust and improved cohesiveness
B. Ground rules for interaction
C. Enhanced resource availability
D. Functional managers becoming more involved

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0358

Project Management Professional (PMP) Exam Practice – Question0357

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?


A.
Resource breakdown structure
B. Staffing management plan
C. Project organizational chart
D. Scope management plan

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0357

Project Management Professional (PMP) Exam Practice – Question0356

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?


A.
Cost management plan
B. Quality management plan
C. Communications management plan
D. Risk management plan

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0356

Project Management Professional (PMP) Exam Practice – Question0355

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?


A.
Bottom-up
B. Parametric
C. Analogous
D. Three-point

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0355

Project Management Professional (PMP) Exam Practice – Question0354

Which document includes the project scope, major deliverables, assumptions, and constraints?


A.
Project charter
B. Project scope statement
C. Scope management plan
D. Project document updates

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0354

Project Management Professional (PMP) Exam Practice – Question0353

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:


A.
Define Activities.
B. Sequence Activities.
C. Define Scope.
D. Control Schedule.

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0353

Posts navigation

Older posts
Newer posts
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored