Project Management Professional (PMP) Exam Practice – Question0351

Requirements documentation will typically contain at least:


A.
Stakeholder requirements, staffing requirements, and transition requirements.
B. Business requirements, the stakeholder register, and functional requirements.
C. Stakeholder impact, budget requirements, and communications requirements.

D. Business objectives, stakeholder impact, and functional requirements.

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question0345

The primary benefit of the Plan Schedule Management process is that it:


A.
provides guidance to identify time or schedule challenges within the project.
B. tightly links processes to create a seamless project schedule.
C. guides how the project schedule will be managed throughout the project.

D. creates an overview of all activities broken down into manageable subsections.

Correct Answer: C