Project Management Professional (PMP) Exam Practice – Question0340

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?


A.
Technical approach
B. Technical capability
C. Business size and type
D. Production capacity and interest

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question0334

Project Scope Management is primarily concerned with:


A.
Developing a detailed description of the project and product.
B. Determining how requirements will be analyzed, documented, and managed.
C. Defining and controlling what is and is not included in the project.
D. Formalizing acceptance of the completed project deliverables.

Correct Answer: C