Project Management Professional (PMP) Exam Practice – Question0220

For any given project, the project manager, in collaboration with the project team, is responsible for:


A.
Applying knowledge, skills, and processes uniformly.
B. Informing the project sponsor about which processes are going to be used.
C. Tailoring the processes to fit the abilities of the organization.
D. Determining which particular processes are appropriate.

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question0218

In the Initiating Process Group, at what point does the project become officially authorized?


A.
When the project charter is signed
B. When all the stakeholders agree on the scope of the project
C. When the project manager is appointed
D. When the necessary finance or funding is obtained

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question0213

What are the five Project Management Process Groups?


A.
Initiating, Planning, Executing, Monitoring and Controlling, and Closing
B. Introduction, Planning, Executing, Monitoring and Controlling, and Closing
C. Initiating, Planning, Executing, Monitoring and Controlling, and Ending
D. Introduction, Planning, Implementation, Monitoring and Controlling, and Closure

Correct Answer: A