Project Management Professional (PMP) Exam Practice – Question0202

Within a matrix organization, dual reporting of team members is a risk for project success. Who is responsible for managing this dual reporting relationship factor?


A.
Functional manager
B. Project manager
C. Functional manager supported by the project manager
D. Project management office

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question0199

A Project Management Office (PMO) manages a number of aspects, including what?


A.
Project scope, schedule, cost, and quality of the products of the work packages
B. Central coordinator of communication management across projects, and for the delivery of specific project objectives, organization opportunity assessment
C. Assigns project resources to best meet project objectives
D. Overall risk, overall opportunity and interdependencies among projects

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question0197

Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?


A.
Qualitative risk analysis
B. Quantitative risk analysis
C. Risk management planning
D. Risk response planning

Correct Answer: A