Project Management Professional (PMP) Exam Practice – Question0168

A project lifecycle is defined as:


A.
a collection of generally sequential and sometimes overlapping project phases.
B. a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
C. a recognized standard for the project management profession.
D. the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question0166

Which characteristics do effective project managers possess?


A.
Project management knowledge, performance skills, and personal effectiveness
B. Preparedness, project management knowledge, and personality characteristics
C. General management, preparedness, and project management knowledge
D. Assertiveness, collaboration, and performance skills

Correct Answer: A