Project Management Professional (PMP) Exam Practice – Question0148

What is the most accurate rough order of magnitude (ROM)?


A.
In the Initiation phase, the estimate is in the range of +/-50%.
B. In the Planning phase, the estimate is in the range of +/-50%.
C. In the Monitoring and Controlling phase, the estimate is in the range of +/-15%.
D. In the Closing phase, the estimate is in the range of +/-15%.

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question0143

Which of the following correctly explains the term "progressive elaboration'?


A.
Changing project specifications continuously
B. Elaborate tracking of the project progress
C. Elaborate tracking of the project specifications with a change control system
D. Project specifications becoming more explicit and detailed as the project progresses

Correct Answer: D