Project Management Professional (PMP) Exam Practice – Question0122

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?


A.
Project Time Management
B. Project Cost Management
C. Project Scope Management

D. Project Human Resource Management

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0122

Project Management Professional (PMP) Exam Practice – Question0121

Which of the following tools and techniques is used in the Verify Scope process?


A.
Inspection
B. Variance analysis
C. Expert judgment
D. Decomposition

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0121

Project Management Professional (PMP) Exam Practice – Question0120

Which type of analysis is used as a general management technique within the Plan Procurements process?


A.
Risk assessment analysis
B. Make or buy analysis
C. Contract value analysis
D. Cost impact analysis

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0120

Project Management Professional (PMP) Exam Practice – Question0119

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?


A.
WBS directory
B. Activity list
C. WBS
D. Project schedule

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0119

Project Management Professional (PMP) Exam Practice – Question0118

What risk technique is used to quantify the probability and impact of risks on project objectives?


A.
Expert judgment
B. Risk registry
C. Risk response planning
D. Interviewing

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0118

Project Management Professional (PMP) Exam Practice – Question0117

Which process determines the risks that might affect the project?


A.
Perform Qualitative Risk Analysis
B. Identify Risks
C. Plan Risk Management
D. Perform Quantitative Risk Analysis

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0117

Project Management Professional (PMP) Exam Practice – Question0116

The project scope statement and resource calendars are inputs to which Project Time Management process?


A.
Sequence Activities
B. Estimate Activity Resources
C. Develop Schedule
D. Control Schedule

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0116

Project Management Professional (PMP) Exam Practice – Question0115

Which of the following is an output of the Distribute Information process?


A.
Project calendar
B. Communications management plan
C. Organizational process assets updates
D. Project document updates

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0115

Project Management Professional (PMP) Exam Practice – Question0114

What causes replanning of the project scope?


A.
Project document updates
B. Project scope statement changes
C. Variance analysis
D. Change requests

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0114

Project Management Professional (PMP) Exam Practice – Question0113

A weighting system is a tool for which area of Conduct Procurements?


A.
Plan contracting
B. Requesting seller responses
C. Selecting seller's
D. Planning purchase and acquisition

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0113

Posts navigation

Older posts
Newer posts
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored