Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Project Management Professional (PMP) Exam Practice

Project Management Professional (PMP) Exam Practice – Question0062

An issue log is an input to which Project Human Resource Management process?


A.
Manage Project Team
B. Acquire Project Team
C. Plan Human Resource Management
D. Develop Project Team

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0062

Project Management Professional (PMP) Exam Practice – Question0061

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:


A.
appetite
B. tolerance
C. threshold
D. management

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0061

Project Management Professional (PMP) Exam Practice – Question0060

Every project creates a unique product, service, or result that may be:


A.
tangible
B. targeted
C. organized
D. variable

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0060

Project Management Professional (PMP) Exam Practice – Question0059

Which element does a project charter contain?


A.
Management reserves
B. Work breakdown structure
C. Stakeholder list
D. Stakeholder register

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0059

Project Management Professional (PMP) Exam Practice – Question0058

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?


A.
Identify Risks
B. Plan Risk Management
C. Perform Qualitative Risk Analysis
D. Perform Quantitative Risk Analysis

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0058

Project Management Professional (PMP) Exam Practice – Question0057

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:


A.
Earned value management.
B. Forecasting.
C. Critical chain methodology.
D. Critical path methodology.

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0057

Project Management Professional (PMP) Exam Practice – Question0056

Technical capability, past performance, and intellectual property rights are examples of:


A.
performance measurement criteria
B. source selection criteria
C. product acceptance criteria
D. phase exit criteria

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0056

Project Management Professional (PMP) Exam Practice – Question0055

The process of defining how the project scope will be validated and controlled is known as:


A.
Define Scope.
B. Develop Project Management Plan.
C. Plan Scope Management.
D. Plan Quality Management.

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0055

Project Management Professional (PMP) Exam Practice – Question0054

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:


A.
influencing
B. leadership

C. motivation
D. coaching

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0054

Project Management Professional (PMP) Exam Practice – Question0053

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?


A.
Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0053