Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:
A. organizational skills B. technical skills C. communication skills D. hard skills
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
A. Plan Stakeholder Management B. Identify Stakeholders C. Manage Stakeholder Engagement D. Control Stakeholder Engagement
A. Consultants and stakeholders B. Stakeholders and functional managers C. Project team members and consultants D. Project team members and stakeholders
In the Plan Stakeholder Management process, expert judgment is used to:
A. Provide information needed to plan appropriate ways to engage project stakeholders. B. Ensure comprehensive identification and listing of new stakeholders. C. Analyze the information needed to develop the project scope statement.
D. Decide the level of engagement of the stakeholders at each required stage.
Which Process Group and Knowledge Area include the Sequence Activities process?
A. Executing Process Group and Project Time Management B. Executing Process Group and Project Cost Management C. Planning Process Group and Project Time Management D. Planning Process Group and Project Cost Management