Project Management Professional (PMP) Exam Practice – Question0022

Which cost is associated with nonconformance?


A.
Liabilities
B. Inspections
C. Training
D. Equipment

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0022

Project Management Professional (PMP) Exam Practice – Question0021

Stakeholder satisfaction should be managed as a key project:


A.
Benefit
B. Initiative
C. Objective
D. Process

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0021

Project Management Professional (PMP) Exam Practice – Question0020

The process of prioritizing risks for further analysis or action is known as:


A.
Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis.

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0020

Project Management Professional (PMP) Exam Practice – Question0019

A temporary endeavor that creates a unique product or service is called a:


A.
Project
B. Plan
C. Program
D. Portfolio

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0019

Project Management Professional (PMP) Exam Practice – Question0018

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?


A.
Requirements documentation
B. Requirements traceability matrix
C. Project management plan updates
D. Project documents updates

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0018

Project Management Professional (PMP) Exam Practice – Question0017

Which process numerically analyzes the effect of identified risks on overall project objectives?


A.
Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0017

Project Management Professional (PMP) Exam Practice – Question0016

An output of the Manage Stakeholder Engagement process is:


A.
change requests
B. enterprise environmental factors
C. the stakeholder management plan
D. the change log

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0016

Project Management Professional (PMP) Exam Practice – Question0015

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:


A.
Responses
B. Appetite
C. Tolerance
D. Attitude

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0015

Project Management Professional (PMP) Exam Practice – Question0014

Which tool or technique is used in the Develop Project Management Plan process?


A.
Pareto diagram
B. Performance reporting
C. SWOT analysis
D. Expert judgment

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0014

Project Management Professional (PMP) Exam Practice – Question0013

Which process involves developing an approximation of the monetary resources needed to complete project activities?


A.
Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0013