Project Management Professional (PMP) Exam Practice – Question2082

The Project Manager has scheduled weekly status meetings with the team. The meetings have been unorganized with multiple people addressing their own needs and taking longer than planned with no discipline. Which of the following would improve the
meetings?


A.
Create and publish an agenda
B. Create and publish an agenda, and establish the leader of the meeting
C. Send the team to communication training
D. Determine who is in charge of the meeting

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question2081

The Project Manager has weekly scheduled status meetings with the team. The meetings have been unorganized, chaotic, and lacking direction. Which of the following would improve the meetings?


A.
Determine who is in charge of the meeting
B. Send the team to communication training
C. Create and publish an agenda, and establish the leader of the meeting
D. Create and publish an agenda

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question2080

A Project Manager has been assigned to manage a project to develop a reduced price desktop computer for a company that does not have this expertise. The project is three weeks behind schedule and under budget. After calculating the estimate at completion
(EAC), the Project Manager finds that project will be $34,589 under budget, but is expected to take four weeks longer than expected. What should the Project Manager do?


A.
Implement Gold Plating to make up for the difference
B. Bill for customer the total approved contracted amount
C. Report the current baseline project status and budget to the customer
D. Report the project status and budget to the customer

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question2079

You are a Project Manager managing the building of a restaurant.
As the electrical wiring is being installed, you cannot find a building permit.
As the Project Manager, to whom do you report this violation?


A.
The construction company
B. The local city authority
C. The local county authority
D. The state authority

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question2078

The sponsor is conducting a meeting and a Project Manager is reporting that his project is behind schedule by three weeks and under budget by $80K US. You discover from the PMO that the project is behind schedule by eight weeks and is over budget. What
should you do?


A.
Notify senior management
B. Report the Project Manager to PMI
C. Ask the PMO to investigate the project status
D. Review with the Project Manager how this status was produced

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question2077

As a Project Manager, your first priority is to accomplish the work of the project. As a result of a project being complete, you have the opportunity to help those on the project become more educated on what worked well and what didn't on the project. What is the
best answer for gaining this experience and knowledge?


A.
Historical information
B. Lessons learned
C. Assumptions
D. Constraints

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question2076

You are the Project Manager on a project where $4M US will be spent on procuring telecom equipment. As negotiations begin between your company and the vendor, you are approached by the vendor's sales representative who offers you a trip to Las Vegas if
you can "help" the process along by ensuring that the contract has accelerated payment terms compared to typical contracts.
What is your professional and social responsibility?


A.
Decline the trip until after the contract has been signed
B. The work you have put in on the project has been demanding and you deserve the trip
C. Decline the trip and have it offered to your manager
D. Decline the trip because it is not in the best interest of the company

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question2075

A Project Manager has been working on quality process of a project at a major defense contractor. The Project Manager discovers that an employee has been reselling some repair material that he has declared as scrap material at a small profit. The item is very
costly. What should the Project Manager do?


A.
Report this to the company
B. Report this to Homeland Security
C. Report this to General Accounting Office (GAO).
D. Report the employee to the local authority

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question2074

You are beginning a new project and a portion of the development will be created by a foreign company. You are not sure how to do business with this company because it is offshore.
What document would be best to guide you in this business?


A.
Companys policies and procedures
B. PMI Code of Conduct
C. Local laws of the offshore company
D. Historical information from past projects

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question2073

As a Project Manager you have a professional and social responsibility to encourage the growth of project management at your company or industry. To help with this growth, you could do all of the following except?


A.
Mentor others who want to learn more about project management
B. Create white papers on project management
C. Provide senior management with information how outsourcing helps their companies
D. Train people on project management

Correct Answer: C