Project Management Professional (PMP) Exam Practice – Question1512

Your project has been under way for some time, but indicators show that it is in trouble. You have observed all the following symptoms of poor teamwork in your project team EXCEPT______________


A.
Frustration
B. Excessive meetings
C. Lack of trust or confidence in the project manager
D. Unproductive meetings

Correct Answer: B

Explanation:

Explanation:
The problem is not too many meetings, but unproductive ones. The purpose of project meetings is to focus the skills and resources of the project team on project performance. Meetings that are considered “gripe sessions” or a time for the project manager to “lay
down the law” are demoralizing to the team.

Project Management Professional (PMP) Exam Practice – Question1511

As a project manager, you believe in using a "personal touch" to further team development. One approach that has proven effective toward this goal is______________


A.
Creating a team name
B. Providing flexible work time
C. Issuing a project charter
D. Celebrating special occasions

Correct Answer: D

Explanation:

Explanation:
Project managers can show interest in their team members by celebrating occasions such as birthdays, anniversaries with the organization, and special achievements. Other approaches include being supportive, being clear, learning some information about each
team member, and being accessible. Through observation and conversation, the project management team monitors indicators such as progress toward project deliverables, accomplishments that are a source of pride for team members, and interpersonal
issues.

Project Management Professional (PMP) Exam Practice – Question1510

Which of the following is an enterprise environmental factor that may influence the development of the human resource management plan?


A.
The organizational structure of the performing organization
B. Poor communication among team members
C. Ambiguous staffing requirements
D. Team morale

Correct Answer: A

Explanation:

Explanation:
Enterprise environmental factors can influence the develop human resource management plan process. The organizational structure of the performing organization determines whether the project manager’s role is a strong one (as in a strong matrix) or a weak
one (as in a weak matrix). Other examples of enterprise environmental factors are the organization’s culture, geographic dispersion of team members, existing human resources, personnel administration functions, and marketplace conditions.

Project Management Professional (PMP) Exam Practice – Question1509

Two team members on your project often disagree. You need a conflict resolution method that provides a long-term resolution. You decide to use which one of the following approaches?


A.
Confronting
B. Problem solving
C. Collaborating
D. Smoothing

Correct Answer: C

Explanation:

Explanation:

Collaborating or problem solving is an effective technique for managing conflict when a project is too important to be compromised. It involves incorporating multiple ideas and viewpoints from people with different perspectives and offers a good opportunity to
learn from others. It provides a long-term resolution.

Project Management Professional (PMP) Exam Practice – Question1508

Constant bickering, absenteeism, and substandard performance have characterized the behavior of certain members of your team. You have planned an off-site retreat for the team to engage in a variety of activities. Your primary objective for investing time and
money in this event is to improve______________


A.
Team performance
B. Morale
C. Quality
D. Individual performance

Correct Answer: A

Explanation:

Explanation:
Team development leads to improved team performance, which ultimately results in improved project performance. Improvements in team performance can come from many sources and can affect many areas of project performance. For example, improved
individual skill levels such as enhanced technical competence may enable team members to perform their assigned activities more effectively. Team development efforts have greater benefit when conducted early but should take place throughout the project life
cycle.

Project Management Professional (PMP) Exam Practice – Question1507

As project manager, you are primarily responsible for implementing the project management plan by authorizing the execution of project activities. Because you do not work in a projectized organization, you do not have direct access to human resource
administrative activities.

Therefore you need to______________


A.
Outsource these functions
B. Prepare a project team charter that is signed off by a member of the human resources department to delineate responsibilities
C. Ensure that your team is sufficiently aware of administrative requirements to ensure compliance
D. Ask the head of human resources to approve your project human resource plan personally

Correct Answer: C

Explanation:

Explanation:
A projectized work environment is unusual because project managers rarely have every function under their control. But compliance with administrative requirements, government regulations, union contract provisions, and other constraints is a consideration in
human resource management.

Project Management Professional (PMP) Exam Practice – Question1506

In both the weak and strong matrix organizational structures, the primary condition leading to conflict is______________


A.
Communication barriers

B. Conflicting interests
C. Need for consensus
D. Ambiguous jurisdictions

Correct Answer: D

Explanation:

Explanation:
Ambiguous jurisdictions exist when two or more parties have related responsibilities, but their work boundaries and role definitions are unclear. This situation is found frequently in weak and strong matrix organizations because of the “two-boss” concept.

Project Management Professional (PMP) Exam Practice – Question1505

It is important on all projects to determine when and how human resources will be met. Assume that you are managing a project to assess methods for streamlining the regulatory approval process for new medical devices in your government agency. Because the
agency has undergone downsizing during the past three years, subject matter experts are in short supply. You must determine whether the needed subject matter experts can be acquired from inside the agency or whether you must use contractors. This
information should be documented in the______________


A.
Make-or-buy decisions in the procurement management plan
B. Contracts management plan
C. Staffing management plan
D. Resource management plan

Correct Answer: C

Explanation:

Explanation:
The staffing management plan is part of the human resource management plan. One section of it involves staff acquisition. Among other things, this section includes whether the human resources will come from within the organization or from external, contracted
sources. These data then help to plan the acquisition of project team members.

Project Management Professional (PMP) Exam Practice – Question1504

You have been a project manager for seven years. You now are managing the construction of a new facility that must comply with the government's newly issued environmental standards. You want to ensure that your team members are able to select methods to
complete various activities on the project without needing to involve you in each situation. As you prepare your human resource management plan, you should document this information in which of the following______________


A.
Roles and responsibilities section
B. Resource assignment matrix
C. Resource breakdown structure
D. Staffing management plan

Correct Answer: A

Explanation:

Explanation:
Authority refers to the right to apply project resources, make decisions, and sign approvals. Examples include selecting methods to complete activities, quality acceptance, and responding to variances in the project. The individual authority of each team member
should match their individual responsibilities. This is documented in the roles and responsibilities section in the human resource management plan.

Project Management Professional (PMP) Exam Practice – Question1503

Given that you are neighbors, you and the CEO of your company have established a friendly personal relationship. Recently your company appointed you project manager for a new project that is crucial to achieving next year's financial targets. Which type of
power available to project managers might you be able to rely upon?


A.
Referent
B. Reward
C. Formal
D. Expert

Correct Answer: A

Explanation:

Explanation:
Referent power is based on a less powerful person’s identification with a more powerful person. This type of power is useful in terms of persuasion and helps the project manager exert influence over individuals from whom he or she needs support.