If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?
A. -11
B. 11
C. -13
D. 13
If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?
A. -11
B. 11
C. -13
D. 13
If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?
A. -1
B. 0
C. 2
D. Cannot be determined
What is the float for Activity G?
A. -2
B. 0
C. 1
D. 4
What is the duration of the critical path in this network?
A. 10
B. 12
C. 14
D. 15