Project Management Professional (PMP) Exam Practice – Question1372

Diagram:

If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?


A.
-11
B. 11
C. -13
D. 13

Correct Answer: B

Explanation:

Explanation:
The late dates for all activities need to be recalculated given the changed duration. Activity G’s revised late dates are______________
LF = 11
LS = 6

Project Management Professional (PMP) Exam Practice – Question1371

Diagram:

If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?


A.
-1
B. 0
C. 2

D. Cannot be determined

Correct Answer: A

Explanation:

Explanation:
The imposed finish date becomes the late finish for Activity I. The late dates for each activity need to be recalculated. The dates for Activity E become______________
ES = 10
EF = 13
LS = 9LF = 12
Total float = LS -ES or 9 -10 = (-1) or
LS -EF or 12 -13 = (-1)

Project Management Professional (PMP) Exam Practice – Question1368

You are establishing a PMO that will have a project management information system that will be an online repository of all program data. You will collect descriptions of all work components for each project under the PMO's jurisdiction. This information will form
an integral part of the______________


A.
Chart of accounts
B. WBS dictionary
C. WBS structure template
D. Earned value management reports

Correct Answer: B

Explanation:

Explanation:
The WBS dictionary typically includes a code of accounts identifier, a statement of work, responsible organization, a list of schedule milestones, associated schedule activities, required resources, cost estimates, quality requirements, acceptance criteria, technical
references, and agreement information.

Project Management Professional (PMP) Exam Practice – Question1367

How is a context diagram used?


A.
To depict product scope
B. To trace requirements as part of the traceability matrix
C. To develop the scope management plan
D. To develop the requirements management plan

Correct Answer: A

Explanation:

Explanation:
It is a tool and technique in collect requirements and is an example of a scope model. The context diagram visually depicts the product scope as it shows a business system (process, equipment, or computer, etc.) and how people and other systems (actors)
interact with it. The diagram shows inputs to the business system, the actor(s) providing the input, outputs from the business system, and actor(s) receiving the output.

Project Management Professional (PMP) Exam Practice – Question1366

The product scope description is documented as part of the project's scope statement. It is important to include it because it______________


A.
Facilitates the project acceptance process
B. Describes specific constraints associated with the project
C. Progressively elaborates characteristics
D. Shows various alternatives considered

Correct Answer: C

Explanation:

Explanation:
The project scope statement describes the deliverables and the work required to create them. It also provides a common understanding of the scope among stakeholders. The product scope statement is a key component as it progressively elaborates the
characteristics of the product, service, or result in the project charter and requirements documentation.

Project Management Professional (PMP) Exam Practice – Question1365

The project scope statement is important in scope control because it______________


A.
Is a critical component of the scope baseline
B. Provides information on project performance
C. Alerts the project team to issues that may cause problems in the future
D. Is expected to change throughout the project

Correct Answer: A

Explanation:

Explanation:
The project scope statement, along with the WBS and WBS dictionary, is a key input to scope control.

Project Management Professional (PMP) Exam Practice – Question1364

You are the project manager for a subcontractor on a major contract. The prime contractor has asked that you manage your work in a detailed manner. Your first step is to______________


A.
Follow the WBS that the prime contractor developed for the project and use the work packages you identified during the proposal
B. Develop a subproject WBS for the work package that is your company's responsibility
C. Establish a similar coding structure to the prime contractor's to facilitate use of a common project management information system
D. Develop a WBS dictionary to show specific staff assignments

Correct Answer: B

Explanation:

Explanation:
Work packages are items at the lowest level of the WBS. A subproject is a smaller portion of the original project when a project is subdivided into more manageable components or pieces. A subproject WBS then breaks down work packages into greater detail. A
subproject WBS generally is used when the project manager assigns a scope of work to another organization, and the project manager at that organization must plan and manage the scope of work in greater detail.