Project Management Professional (PMP) Exam Practice – Question1342

You want to structure your project so that each project team member has a discrete work package to perform. The work package is a______________


A.
Deliverable at the lowest level of the WBS
B. Task with a unique identifier
C. Required level of reporting
D. Task that can be assigned to more than one organizational unit

Correct Answer: A

Explanation:

Explanation:
A work package is the lowest or smallest unit of work division in a project or WBS. The work package can be scheduled, cost estimated, monitored, and controlled.

Project Management Professional (PMP) Exam Practice – Question1341

The first step in collecting requirements on any project, large or small, is to______________


A.
Talk with the project stakeholders through interviews
B. Review the scope management plan
C. Conduct facilitated workshops with stakeholders
D. Prepare a requirements document template that you and your team can use throughout the collect requirements process

Correct Answer: B

Explanation:

Explanation:
The scope management plan is reviewed first as it provides clarity as to how the project team will determine which requirements need to be collected on the project.

Project Management Professional (PMP) Exam Practice – Question1340

The project scope statement addresses and documents all the following items EXCEPT______________


A.
Project exclusions
B. The relationship between the deliverables and the business need
C. Product scope description
D. Project management methodology (PMM)

Correct Answer: B

Explanation:

Explanation:
The PMM is an organization-approved approach for project management that is used on every project. It is not part of the project scope statement, which describes the project scope, major deliverables, assumptions, and constraints. It describes the project’s
deliverables and the work required to complete them.

Project Management Professional (PMP) Exam Practice – Question1339

Collecting requirements is critical in project scope management as it becomes the foundation for the project's______________


A.
Scope management plan
B. WBS
C. Schedule
D. Scope change control system

Correct Answer: B

Explanation:

Explanation:
Collecting requirements provides the basis for defining project scope and product scope. It also involves determining, documenting, and managing stakeholder needs to meet project objectives. The requirements become the foundation for the WBS; moreover,
cost, schedule, and quality planning are built upon the requirements.

Project Management Professional (PMP) Exam Practice – Question1338

Rather than use a WBS, your team developed a bill of materials to define the project's work components. A customer review of this document uncovered that a scope change was needed, because a deliverable had not been defined, and a change request was
written subsequently. This is an example of a change request that was the result of______________


A.
An external event
B. An error or omission in defining the scope of the product
C. A value-adding change
D. An error or omission in defining the scope of the project

Correct Answer: B

Explanation:

Explanation:
The bill of materials provides a hierarchical view of the physical assemblies, subassemblies, and components needed to build a manufactured product, whereas the WBS is a deliverable-oriented grouping of project components used to define the total scope of
the project, providing a structured vision of what has to be delivered. Using a bill of materials where a WBS would be more appropriate may result in an ill-defined scope and subsequent change requests.

Project Management Professional (PMP) Exam Practice – Question1337

During the closing of a complex project that includes several stakeholders, the project manager initiates a satisfaction evaluation. The contact information for one of the stakeholders is inaccurate.

What should the project manager do to obtain accurate stakeholder information?


A.
Contact the stakeholders individually.
B. Ask the sponsor for the updated stakeholder information.
C. Review the stakeholder engagement plan.
D. Refer to the stakeholder register.

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question1336

During the final stages of project execution, a dissatisfied customer requests that a feature be removed. The request is approved and will help complete the project on time.
What should the project manager do next?


A.
Review the changes with the project team.
B. Revise the communications management plan.
C. Reduce project resources to decrease costs.
D. Update the project scope baseline.

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question1335

After completion of one phase for a new product development project, the project manager realizes that the marketing departments acceptance criteria is missing.
What should the project manager do next?


A.
Initiate a change request to include the missing acceptance criteria.
B. Meet the marketing department to obtain their acceptance criteria.
C. Ask the sponsor to increase the budget to compensate for the missing acceptance criteria.
D. Negotiate with the marketing department to exclude their acceptance criteria.

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1333

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?


A.
Fixed Price with Economic Price Adjustments Contract (FP-EPA)
B. Cost-Reimbursable Contract (CR)
C. Firm-Fixed -Price Contract (FFP)
D. Fixed-Price-Incentive-Fee Contract (FPIF)

Correct Answer: C