Project Management Professional (PMP) Exam Practice – Question1319

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?


A.
Organizational process assets
B. A work breakdown structure

C. The project management plan
D. Enterprise environmental factors

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question1313

A multinational project includes stakeholders from various locations and cultures. During the final acceptance stage, a new stakeholder is added who refuses to provide final approval.
What should the project manager do?


A.
Review the project acceptance criteria with the new stakeholder
B. Contact the previous stakeholder for a resolution
C. Escalate the issue with the sponsor
D. Issue a formal change request

Correct Answer: A