Project Management Professional (PMP) Exam Practice – Question1312

Following a review of the completed final project phase, customer feedback is positive and formal acceptance of the deliverable is obtained.
What is the output of this meeting?


A.
Work performance information
B. Project document updates
C. Organizational process assets updates
D. Closed procurements

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question1304

Which Knowledge Areas include processes from the Closing Process Group?


A.
Project Quality Management and Project Time Management
B. Project Scope Management and Project Risk Management
C. Project Stakeholder Management and Project Cost Management
D. Project Integration Management and Project Procurement Management

Correct Answer: D