Project Management Professional (PMP) Exam Practice – Question1252

All the deliverables defined in a project have been completed. In the final meeting to approve these deliverables, some stakeholders state that the product does not meet their needs.
What should the project manager do?


A.
Demonstrate that the objectives in the project charter have been achieved.
B. Validate that the deliverables are as requested and close the project.
C. Demonstrate that the deliverables have been verified and negotiate their approval.
D. Review the list of stakeholders and determine whether the appropriate individuals attended the meeting.

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question1250

A project sponsor asks to terminate a software installation project that is 80 percent complete. What should the project manager do first?


A.
Follow the project management plan to close the project.
B. Meet with the sponsor to discuss the possibility of continuing the project.
C. Release the project team to other projects.
D. Proceed to complete the installation, then close the project.

Correct Answer: B

Project Management Professional (PMP) Exam Practice – Question1249

The Closing Process Group includes which of the following Knowledge Areas?


A.
Project Risk Management and Project Procurement Management
B. Project Integration Management and Project Procurement Management
C. Project Risk Management and Project Integration Management
D. Project Integration Management and Project Quality Management

Correct Answer: B