Project Management Professional (PMP) Exam Practice – Question1214

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:


A.
training, testing, and warranty work.
B. equipment, rework, and scrap.
C. training, document processes, and inspections.
D. inspections, rework, and warranty work.

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question1213

Which of the following characteristics are found in a functional organizational structure?


A.
Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget
B. Limited project manager authority, limited resource availability, and a part-time project manager's role
C. Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role
D. High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Correct Answer: A