Project Management Professional (PMP) Exam Practice – Question1202

A projects latest earned value (EV) report indicates that a certain task has an estimate at completion (EAC) of US$550,000 and a budget at completion (BAC) of US$500,000.
What should the project manager experience will this task?


A.
A budget overrun on completion
B. Completion under budget
C. Completion exactly on budget
D. A budget needing sponsor approval to continue

Correct Answer: A

Project Management Professional (PMP) Exam Practice – Question1201

A project manager identifies an issue and assigns it to a stakeholder. After several weeks and numerous reminders, the stakeholder has still failed to resolve the issue.
What should the project manager do next?


A.
Escalate the issue to senior management.
B. Convert the issue to a risk.
C. Use emotional intelligence to influence the stakeholder to resolve the issue.
D. Employ other communication channels for that stakeholder.

Correct Answer: D

Project Management Professional (PMP) Exam Practice – Question1196

The Monitoring and Controlling Process Group includes processes that:


A.
Establish the scope, objectives, and course of action of a project,

B. Define a new project or a new phase of an existing project.
C. Track, review, and regulate the progress and performance of a project.
D. Complete the work defined in the project management plan.

Correct Answer: C

Project Management Professional (PMP) Exam Practice – Question1195

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?


A.
External
B. Internal
C. Mandatory
D. Discretionary

Correct Answer: D