Project Management Professional (PMP) Exam Practice – Question0013

Which process involves developing an approximation of the monetary resources needed to complete project activities?


A.
Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0013