Project Management Professional (PMP) Exam Practice – Question0029

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?


A.
Plan Stakeholder Management
B. Identify Stakeholders
C. Manage Stakeholder Engagement
D. Control Stakeholder Engagement

Correct Answer: A