Project Management Professional (PMP) Exam Practice – Question0040

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?


A.
Collect Requirements
B. Plan Scope Management
C. Define Scope
D. Define Activities

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0040