Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0053

Project Management Professional (PMP) Exam Practice – Question0053

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?


A.
Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0053
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored