Project Management Professional (PMP) Exam Practice – Question0089

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?


A.
Organizational standard processes
B. Marketplace conditions
C. Historical information
D. Templates

Correct Answer: B