Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0113

Project Management Professional (PMP) Exam Practice – Question0113

A weighting system is a tool for which area of Conduct Procurements?


A.
Plan contracting
B. Requesting seller responses
C. Selecting seller's
D. Planning purchase and acquisition

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0113