Project Management Professional (PMP) Exam Practice – Question0120

Which type of analysis is used as a general management technique within the Plan Procurements process?


A.
Risk assessment analysis
B. Make or buy analysis
C. Contract value analysis
D. Cost impact analysis

Correct Answer: B