Project Management Professional (PMP) Exam Practice – Question0131

Which of the following is a tool and technique used in the Develop Schedule process?


A.
Three-point estimates
B. Resource leveling
C. Precedence diagramming method
D. Bottom-up estimating

Correct Answer: B