Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0155

Project Management Professional (PMP) Exam Practice – Question0155

The process of identifying specific actions to be performed to produce project deliverables is:


A.
Define Activities.
B. Create WBS.
C. Define Scope.
D. Develop Schedule.

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0155
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored