Projects are separated into phases or subprojects; these phases include:


A.
feasibility study, concept development, design, and prototype.
B. initiate, plan, execute, and monitor.
C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.
D. Identify Stakeholders, develop concept, build, and test.

Correct Answer: A