Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0170

Project Management Professional (PMP) Exam Practice – Question0170

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?


A.
Scope baseline
B. Scope management plan
C. Change management plan
D. Cost baseline

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0170
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored