Which of the following response strategies are appropriate for negative risks or threats?


A.
Share, Accept, Transfer, or Mitigate
B. Exploit, Enhance, Share, or Accept
C. Mitigate, Share, Avoid, or Accept
D. Avoid, Mitigate, Transfer, or Accept

Correct Answer: D