Project Management Professional (PMP) Exam Practice – Question0185

The probability and impact matrix is primarily used to:


A.
Quantify risk issues for trends during a quality audit.
B. Develop a risk register for risk planning.
C. Evaluate each risks importance and priority during Perform Qualitative Risk Analysis.
D. Define risk and compare impacts during Perform Quantitative Risk Analysis.

Correct Answer: C