Project Management Professional (PMP) Exam Practice – Question0248

A project manager has only a short timeframe in which to complete a projects cost estimation. What estimating technique should the project manager use?


A.
Top-down
B. Three-point
C. Bottom-up
D. Analogous

Correct Answer: D