Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?


A.
Interrelationship digraphs
B. Tree diagram
C. Affinity diagram
D. Network diagram

Correct Answer: B