Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0292

Project Management Professional (PMP) Exam Practice – Question0292

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?


A.
Facilitation techniques
B. Expert judgment
C. Analytical techniques

D. Variance analysis

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0292