Project Management Professional (PMP) Exam Practice – Question0300

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?


A.
Timing
B. Methodology
C. Risk categories
D. Budgeting

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0300