Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0312

Project Management Professional (PMP) Exam Practice – Question0312

When does the project team determine which dependencies are discretionary?


A.
Before the Define Activities process
B. During the Define Activities process
C. Before the Sequence Activities process
D. During the Sequence Activities process

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0312