Project Management Professional (PMP) Exam Practice – Question0313

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?


A.
Develop Schedule
B. Create VVBS
C. Estimate Activity Resources
D. Define Scope

Correct Answer: B