Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0320

Project Management Professional (PMP) Exam Practice – Question0320

The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?


A.
10
B. 12
C. 14
D. 16

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0320
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored