Project Management Professional (PMP) Exam Practice – Question0333

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?


A.
Strong
B. Weak
C. Managed
D. Balanced

Correct Answer: D