Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0344

Project Management Professional (PMP) Exam Practice – Question0344

The following is a network diagram for a project.

The free float for Activity H is how many days?


A.
4
B. 5
C. 10
D. 11

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0344
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored