Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0349

Project Management Professional (PMP) Exam Practice – Question0349

The following is a network diagram for a project.

The total float for the project is how many days?


A.
3
B. 5
C. 7
D. 9

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0349
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored