A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance? 
A. -700 
B. -200 
C. 200 
D. 500
-700 
B. -200 
C. 200 
D. 500