Project Management Professional (PMP) Exam Practice – Question0389

Quality metrics are an output of which process?


A.
Plan Quality
B. Perform Quality Control
C. Perform Quality Assurance
D. Perform Qualitative Risk Analysis

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0389