Project Management Professional (PMP) Exam Practice – Question0510

After preparation of the project management plan, the project manager schedules a meeting with key stakeholders. What part of the project will this complete?


A.
Evaluation
B. Planning
C. Initiation
D. Execution

Correct Answer: B